A completes a work in 20 days B in 60 days C in 45 days.  All three persons working together on a project got a profit of Rs.26000 what is the profit of B?

in progress 0
Time & Work Admin 3 years 1 Answer 688 views 0

Answer ( 1 )

  1. Maswood Khan

    Please briefly explain why you feel this answer should be reported .

    Report
    Cancel

    when all of them are working together, profit will be divided among them according to the their working capacities.
    So, profit ratio will be 1/20:1/60:1/45 for A,B and C respectively.
    After simplifying the ratio it will become 9:3:4

    Hence, B’s profit would be = 3/16*26000 = 4875 Rs